|
PROJECT AUTHORIZATION |
PACKET ID: PMT-I0HC |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
6898801D 6898801R |
68988 |
13 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
|
|
01-00330 |
1-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
NEW ROUTE |
3.3000 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
|
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
|
STATE |
|
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
1-330 |
D |
1100 |
FD04 |
|
2022 |
|
$400,000.00 |
1-330 |
R |
1100 |
FD04 |
|
2022 |
|
($400,000.00) |
CURRENT FUNDING REQUEST TOTAL: $0.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$2,150,000.00 |
UTILITIES |
$150,000.00 |
R/W |
$5,291,212.49 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $7,591,212.49 |
THIS MODIFICATION TRANSFERS $400,000 FD04 FUNDS FROM THE RIGHT OF WAY PHASE (6898801R) TO THE DESIGN PHASE (6898801D). |
|
Project Approval Recommended By:
James Ballinger 11/24/2021 |
Signed and Approved by:
Jim Gray 11/24/2021 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
01-00330.00 |
LIVINGSTON
|
1 |
PADUCAH - SMITHLAND |
US 60 |
3.3000 MI |
PADUCAH-HENDERSON; RELOCATE US-60 FROM EAST OF THE TENNESSEE RIVER BRIDGE TO EAST OF RUDD-SPEES ROAD (00CCR)(12CCR)(14CCR) (2020CCR) |